Interior Building Demolition Near Completion

Building A- Second floor

Building A- Second floor

Interior building demolition is essentially complete with the removal of the non-structural walls. Initiating HEPA vacuuming of the surfaces to remove dust and adding an application of “lock down agent” to further control dust. Anticipate building demolition to begin Summer 2015. For more progress photos, see NTCRA Progress.

Last updated on April 15, 2015