Total Groundwater Processed

Through mid-June, 2019, approximately 1.35 million gallons of groundwater have been processed through the Permanent Groundwater Treatment System (Final Treatment System), which has been operational since April 2, 2019.

Previously, approximately 17 million gallons of groundwater were processed through the Temporary Groundwater Treatment System (TGTS) to maintain hydraulic capture of the plume. The TGTS operated from May 23, 2017 until the Final Treatment System was operational.

Groundwater NTCRA

  • Groundwater NTCRA Documents
  • Groundwater – Completed Activities
  • Groundwater – Upcoming Activities
  • GW NTCRA Progress Photos
  • Baseline Ecological Risk Assessment Documents

Updates

  • Latest News
  • Community Involvement & Events

Introduction

  • Site History
  • Contaminants of Concern
  • Relevant EPA Guidance

Building Demolition
Non-Time Critical
Removal Action (NTCRA)

  • NTCRA Progress
  • Activities – Completed
  • Activities – Upcoming
  • NTCRA Related Documents

Environmental Remediation
Remedial Investigation /
Feasibility Study (RI/FS)

  • Activities – Completed
  • Activities – Upcoming
  • RI/FS Related Documents
  • Interactive NMI Site Overview

Quick Links

  • U.S. EPA NMI Site information page
  • The Citizens Research & Environmental Watch (CREW) website
  • The Town of Concord Geographical Information System (GIS) website
  • 2229 Main Street website

RSS FeedsSubscribe to Nuclear Metals RSS Feed

Public Meeting 28OCT2003 Part 2

Public Meeting 28OCT2003 Part1

Fall05 U235 BR val

Figure 2-3 Overburden Uranium

Public Meeting 28OCT2003

Drum Excavation Presentation

Risk Presentation MAR2010

NTCRA CFD Permit Equivalency 18NOV2011

NMI NTCRA Action Memo 23SEP2008

Cylinder Removal Plan Rev3 13SEP2012